Skip to main content
Find a Crown Development Application

This is a beta service - your feedback will help us to improve it

Back to list

CROWN/2025/0000002 Robert Stevenson (Canterbury Diocesan Board of Finance Limited) on behalf of Canterbury Diocesan Board of Finance Limited

Date submitted
11 Sep 2025
Submitted by
Interested Party

Introduction 1 The development of the SIBF site has already caused substantial harm to the setting of the Grade I Listed Building, St Mary’s Church, Sevington. This impact was meant to be mitigated in three ways as part of the development consent: • Protected views through the commercial site. • A 30-bay church car park. • A circa £200,000 contribution to ‘church works’ before development commences. 2 The first two were implemented but the third has not so far been forthcoming. There is an urgent need for church works funding and the Crown Development should not be approved in the absence of a legal obligation to make the overdue payment to enable works to proceed. Background 3 The 120-acre site was a Local Plan allocation for a logistics hub. The owners secured planning permission(14/00906/AS) in September 2017 for 1.7 million square feet of warehousing. 4 In a letter dated 23.10.2014(Appendix) English Heritage raised strong objections because of harm to the setting and sustainability of St Marys. The EH response was expressed in strong terms and included the following key paragraphs.(See Document) 5 It is not credible to suggest that the SIBF has had any less impact on the setting of St Mary’s than the original commercial development proposal. A key element of the significance of the Grade 1 Listed Building was its ‘strong sense of agricultural setting’(above) and its ‘commanding presence’ over the countryside. The SIBF has all but destroyed this setting and any suggestion that the harm has been ’less than substantial’ is surprising and cannot be relied upon. This may stem from the assessment methodology applied by the applicants which was designed for judging the impact of roads and bridges not a nationally significant infrastructure development covering a site of 120 acres. 6 The package of mitigation measure summarised above were incorporated as formal requirements through the conditions attached to the original planning permission for the commercial development and the integral S106 Agreement. The owners sold the site to Department for Transport in July 2020 with the above obligations novated to DfT. 7 The Sevington Inland Border Facility(SIBF) was approved by Central Government under a Special Development Order(SDO). A subsequent Lawful Development Certificate 19/01099/AS confirmed that works had commenced lawfully on 31.7.19. 8 DfT accepted that the IBF caused substantial harm to the setting of St Mary’s and that the church works contribution should have been paid before development commenced. Unfortunately, this did not happen. DfT took the position that a new S106 Agreement was required and that payment could not be made until a new Agreement had been made. Although the agreement was ready by the end of 2022, for various reasons DfT declined to sign the Agreement and argued it could not make the payment as a result. 9 So, the substantial harm to the setting of St Mary’s anticipated by the parties has occurred and its physical condition has deteriorated considerably. Notably the spire is in poor conditions because of the loss of oak shingles and the ingress of rain and pigeons. The volume of droppings from the latter is causing significant damage. Unilateral Undertaking 10 DfT now propose a Unilateral Undertaking incorporating the following provisions relevant to St Mary’s: (See document) 11 The ‘Condition Precedent’ clause on p.4 of the Draft Unilateral Undertaking means that, in effect, the contributions would not be made until 8 weeks after the date of the planning permission decision notice. Legal and Policy Compliance 12 Completion of the mitigation measures incorporated into the Draft Unilateral Undertaking are essential to ensure legal and policy compliance, including the following provisions. • Town and Country Planning Act 1990 S70(2). • Planning and Compulsory Purchase Act 204 S38(6). • Planning(Listed Buildings and Conservation Areas) Act 1990 relevant provisions. • National Planning Practice Guidance historic environment provisions. • Section 16 of the National Planning Policy Framework and paragraphs 207, 208, 209, 210, 212, 213 and 214. • Ashford Local Plan 2030 policies SP1 and ENV13. Response of Canterbury Diocese 13 The Crown Development Application is effectively seeking retrospective consent on a permanent basis for a development which has already caused substantial harm to an important heritage asset. It is therefore extremely important that permission is only granted with a legally binding agreement in place that makes the payment of the church works contribution mandatory within a very short space of time after the decision notice is issue. 14 The remedy of a Unilateral Undertaking as now proposed by DfT is essential if the harm that has already taken place is to be reduced and future serious deterioration of the important heritage asset, St Mary’s Church, is to be prevented.. Conclusions 15 The Inspector is respectfully invited to conclude that the Crown Development Order should not be approved unless there is an effective formal mechanism to ensure that the church works contribution is made in a timely manner, taking into account the harm already caused to the heritage asset and the inevitable decline of the Grade Listed Building if there are any further delays in the funds coming forward. Appendix Letter dated 23.10.2014 from English Heritage regarding the impact of development on St Marys Sevington. ~ ~ ~

Attachment(s)